Roadwork To Effect Traffic Pattern, Parking
Lamps Road, connecting the large Fire & Emergency Services parking lot to Patrol Road will be closed to vehicular traffic from Oct. 14-31 while Otak Group, Inc. installs a new sidewalk efrom the parking lot area to Building 1343, according to Joann Mason of NAVFAC SE.
"This closure is necessary to allow additional safety measures for the personnel transiting this area walking and safe access for the contractors' construction of the sidewalk," she said.
On Oct. 12-13, the Bank of America parking lot will be closed while crew resurface the parking lot and the Foc'sle Lounge/Surfside Fitness parking lot will be closed on Oct. 13-14 for the same treatment. Since most of the work is being performed on the weekend or holiday, there should be minimal impact for the resurfacing project. The work will also be completed in two phases to allow some parking availability at the sites.